2018

Late 2018

Detailed design work on the heritage core, open space, employment areas and main spine road including site investigations and necessary surveys started.

2019

2019

Bolton at Home, Irwell Valley commences.

2021

2021

Morris Homes site works commence.

2022

2022

Bellway Phase 2 development commences.

2023

2023

Spine road construction commences across site

2024

2024

Bellway phase 3 development commences.

2025

2025

Planning submitted for final remediation works and strategic open space.
Final stage of road infrastructure in place.

2026

2026

Zone A and open space development underway.
Phase 4 & Homes England phases to commence.

2027

2027

Heritage Core development underway.

2028

2028

Final development phases commenced.
Road infrastructure fully opened up across site.