2018
Late 2018
Detailed design work on the heritage core, open space, employment areas and main spine road including site investigations and necessary surveys started.
2019
2019
Bolton at Home, Irwell Valley commences.2021
2021
Morris Homes site works commence.
2022
2022
Bellway Phase 2 development commences.
2023
2023
Spine road construction commences across site2024
2024
Bellway phase 3 development commences.
2025
2025
Planning submitted for final remediation works and strategic open space.
Final stage of road infrastructure in place.
2026
2026
Zone A and open space development underway.
Phase 4 & Homes England phases to commence.
2027
2027
Heritage Core development underway.
2028
2028
Final development phases commenced.
Road infrastructure fully opened up across site.